Battery Engineering Platform - Proposed Baseline Rev 0.1

Battery Engineering Platform - Proposed Baseline Rev 0.1

UID:
VERSION:
CLASSIFICATION:
PREFIX:
Type
Level
UID
STATUS
DOMAIN
PARENT
REFS
Title
Statement
ACCEPTANCE
METHOD
VMODEL_LEVEL
RELEASE
PRIORITY
OWNER
SOURCE
TEST_IDS
HAZARD_IDS
EXECUTION
IMPLEMENTATION
REQUIREMENT
1
STK-001
Draft
Stakeholder
STK-001
STK-001 - Stakeholder

The product shall provide a replaceable 12.8 V nominal rechargeable energy source.

4S1P LFP reference architecture reviewed against intended load.

Review

Validation

V1-12V

Must

Unassigned

Engineering target - proposed

Not Run

REQUIREMENT
2
STK-002
Draft
Stakeholder
STK-002
STK-002 - Stakeholder

The product shall support an agreed load and charger envelope.

Electrical load profile and charger profile approved with voltage/current/pulse ranges.

Review

Validation

V1-12V

Must

Unassigned

Engineering target - proposed

HZ-005

Not Run

REQUIREMENT
3
STK-003
Draft
Stakeholder
STK-003
STK-003 - Stakeholder

The product shall prevent hazardous electrical and thermal operating states.

Hazard review identifies controls and verification for each unacceptable risk.

Review

Validation

V1-12V

Must

Unassigned

Engineering target - proposed

Not Run

REQUIREMENT
4
STK-004
Draft
Stakeholder
STK-004
STK-004 - Stakeholder

The engineering platform shall allow remote access to released engineering designs.

Authorized browser can retrieve released CAD view, requirements, BOM, and reports.

Demo

Validation

V1-12V

Must

Unassigned

Engineering target - proposed

Not Run

REQUIREMENT
5
STK-005
Draft
Stakeholder
STK-005
STK-005 - Stakeholder

The platform shall trace design decisions to requirements and verification evidence.

Sample 10 requirements traced bidirectionally through implementation and test reports.

Inspection

Validation

V1-12V

Must

Unassigned

Engineering target - proposed

Not Run

REQUIREMENT
6
STK-006
Draft
Stakeholder
STK-006
STK-006 - Stakeholder

The project shall maintain a costed production BOM and approved alternatives.

100% of released purchasable parts have source, quantity, cost and lifecycle status.

Inspection

Validation

V1-12V

Must

Unassigned

Engineering target - proposed

Not Run

REQUIREMENT
7
STK-007
Draft
Stakeholder
STK-007
STK-007 - Stakeholder

The product family shall support 24 V, 48 V and 72 V-class variants through controlled reuse.

Family architecture defines reusable and variant-specific assets with no safety assumptions inherited implicitly.

Review

Validation

V1-12V

Must

Unassigned

Engineering target - proposed

Not Run

REQUIREMENT
8
STK-008
Draft
Stakeholder
STK-008
STK-008 - Stakeholder

The product shall be serviceable using documented diagnostics and replaceable assemblies.

Documented diagnostic workflow identifies each specified field-replaceable assembly.

Demo

Validation

V1-12V

Must

Unassigned

Engineering target - proposed

Not Run

REQUIREMENT
9
STK-009
Draft
Stakeholder
STK-009
STK-009 - Stakeholder

The product shall meet the environmental and mechanical needs of its intended use.

Environmental profile and corresponding qualification plan approved.

Review

Validation

V1-12V

Must

Unassigned

Engineering target - proposed

Not Run

REQUIREMENT
10
STK-010
Draft
Stakeholder
STK-010
STK-010 - Stakeholder

The project shall support independent review and controlled engineering releases.

Each released baseline carries approver, version, date and evidence manifest.

Inspection

Validation

V1-12V

Must

Unassigned

Engineering target - proposed

Not Run

REQUIREMENT
11
SYS-001
Draft
System
STK-001
SYS-001
SYS-001 - System

The V1 pack shall contain four LFP cells connected in series.

As-built cell count=4 and measured polarity/topology matches schematic.

Inspection

System

V1-12V

Must

Unassigned

Engineering target - proposed

TR-001

Not Run

REQUIREMENT
12
SYS-002
Draft
System
STK-001
SYS-002
SYS-002 - System

The V1 reference energy shall be 256 Wh nominal.

4 × 3.2 V × 20 Ah = 256 Wh in approved reference model.

Analysis

System

V1-12V

Must

Unassigned

Engineering target - proposed

Not Run

REQUIREMENT
13
SYS-003
Draft
System
STK-002
SYS-003
SYS-003 - System

The V1 pack shall support 20 A continuous discharge at the specified ambient and SOC.

Validated steady-state load profile maintained without exceeding approved electrical/thermal limits.

Test

System

V1-12V

Must

Unassigned

Engineering target - proposed

Not Run

REQUIREMENT
14
SYS-004
Draft
System
STK-002
SYS-004
SYS-004 - System

The V1 pack shall support 10 A charging where the cell supplier permits.

Charge test at 10 A passes supplier temperature, voltage, and current limits.

Test

System

V1-12V

Must

Unassigned

Engineering target - proposed

HZ-005

Not Run

REQUIREMENT
15
SYS-005
Draft
System
STK-003
SYS-005
SYS-005 - System

The pack shall interrupt charge/discharge according to the approved protection state table.

Each listed fault produces expected output state and recorded event.

Test

System

V1-12V

Must

Unassigned

Engineering target - proposed

TR-004, TR-005

HZ-001

Not Run

REQUIREMENT
16
SYS-006
Draft
System
STK-003
SYS-006
SYS-006 - System

Pack overcurrent/short-circuit protection shall not depend on a cloud connection.

Connectivity removed; hardware protection remains functional in supervised bench test.

Test

System

V1-12V

Must

Unassigned

Engineering target - proposed

TR-007

HZ-002

Not Run

REQUIREMENT
17
SYS-007
Draft
System
STK-003
SYS-007
SYS-007 - System

The pack shall incorporate a coordinated fuse and electronic protection concept.

Safety review validates fuse ratings, FET SOA, fault energy, wiring, and disconnection behavior.

Analysis

System

V1-12V

Must

Unassigned

Engineering target - proposed

HZ-002, HZ-007

Not Run

REQUIREMENT
18
SYS-008
Draft
System
STK-002
SYS-008
SYS-008 - System

The pack shall expose a defined service interface for diagnostics.

All protocol commands pass interface conformance tests.

Test

System

V1-12V

Must

Unassigned

Engineering target - proposed

Not Run

REQUIREMENT
19
SYS-009
Draft
System
STK-009
SYS-009
SYS-009 - System

The pack shall comply with an approved system operating envelope.

Operating envelope table approved and full boundary-condition test coverage assigned.

Review

System

V1-12V

Must

Unassigned

Engineering target - proposed

Not Run

REQUIREMENT
20
SYS-010
Draft
System
STK-005
SYS-010
SYS-010 - System

Every completed system test shall identify the tested hardware and firmware revisions.

Test artifacts contain immutable HW rev, FW hash, instrument calibration, date.

Inspection

System

V1-12V

Must

Unassigned

Engineering target - proposed

Not Run

REQUIREMENT
21
CEL-001
Draft
Cell
SYS-001
CEL-001
CEL-001 - Cell

Each cell shall be traceable to an approved manufacturer and part number.

Serial/lot, source datasheet and supplier documented for every prototype cell.

Inspection

Component

V1-12V

Must

Unassigned

Engineering target - proposed

HZ-003

Not Run

REQUIREMENT
22
CEL-002
Draft
Cell
SYS-001
CEL-002
CEL-002 - Cell

The selected cell shall provide at least 20 Ah nominal capacity under its specified conditions.

Manufacturer spec confirmed and capacity acceptance test method approved.

Test

Component

V1-12V

Must

Unassigned

Engineering target - proposed

Not Run

REQUIREMENT
23
CEL-003
Draft
Cell
SYS-009
CEL-003
CEL-003 - Cell

The design shall prevent cell operation outside supplier charge temperature limits.

Boundary test inhibits charge as required by frozen cell specification.

Test

Component

V1-12V

Must

Unassigned

Engineering target - proposed

Not Run

REQUIREMENT
24
CEL-004
Draft
Cell
SYS-009
CEL-004
CEL-004 - Cell

The design shall prevent cell operation outside supplier discharge temperature limits.

Boundary test inhibits discharge as required by frozen cell specification.

Test

Component

V1-12V

Must

Unassigned

Engineering target - proposed

Not Run

REQUIREMENT
25
CEL-005
Draft
Cell
SYS-001
CEL-005
CEL-005 - Cell

Cell model parameters shall identify manufacturer, chemistry, revision and test conditions.

Model dataset contains provenance and temperature/current metadata.

Inspection

Component

V1-12V

Must

Unassigned

Engineering target - proposed

Not Run

REQUIREMENT
26
CEL-006
Draft
Cell
SYS-001
CEL-006
CEL-006 - Cell

Cell selection shall include a defined matching and incoming quality procedure.

Incoming inspection evaluates approved capacity, resistance and visual criteria.

Test

Component

V1-12V

Must

Unassigned

Engineering target - proposed

Not Run

REQUIREMENT
27
CEL-007
Draft
Cell
SYS-009
CEL-007
CEL-007 - Cell

Cell compression and orientation shall conform to supplier mechanical limits.

Approved fixture and compression specification reviewed against supplier data.

Inspection

Component

V1-12V

Must

Unassigned

Engineering target - proposed

Not Run

REQUIREMENT
28
ELE-001
Draft
Electrical
SYS-005
ELE-001
ELE-001 - Electrical

The system shall measure every series-cell voltage independently.

Four channels mapped and calibrated against reference instrument.

Test

Subsystem

V1-12V

Must

Unassigned

Engineering target - proposed

TR-002

HZ-001

Not Run

REQUIREMENT
29
ELE-002
Draft
Electrical
SYS-005
ELE-002
ELE-002 - Electrical

Cell voltage measurement error shall remain within the approved error budget.

Measured worst-case absolute error <= frozen sensing accuracy budget.

Test

Subsystem

V1-12V

Must

Unassigned

Engineering target - proposed

TR-003

Not Run

REQUIREMENT
30
ELE-003
Draft
Electrical
SYS-005
ELE-003
ELE-003 - Electrical

Pack current shall be measured in both charge and discharge directions.

Calibrated positive and negative currents within approved sensing error budget.

Test

Subsystem

V1-12V

Must

Unassigned

Engineering target - proposed

Not Run

REQUIREMENT
31
ELE-004
Draft
Electrical
SYS-005
ELE-004
ELE-004 - Electrical

The system shall detect an open cell-sense lead or enter a defined safe state.

Each applicable sense-lead disconnect produces mapped fault/safe state.

Test

Subsystem

V1-12V

Must

Unassigned

Engineering target - proposed

TR-006

HZ-008

Not Run

REQUIREMENT
32
ELE-005
Draft
Electrical
SYS-007
ELE-005
ELE-005 - Electrical

Protection switches shall withstand approved continuous, pulse and fault operating cases.

Thermal, SOA and transient calculations signed off; representative tests pass.

Analysis

Subsystem

V1-12V

Must

Unassigned

Engineering target - proposed

HZ-007

Not Run

REQUIREMENT
33
ELE-006
Draft
Electrical
SYS-007
ELE-006
ELE-006 - Electrical

The battery shall have a fuse coordinated with conductor and fault energy limits.

Fuse I²t, expected prospective short current and conductor limits reviewed.

Analysis

Subsystem

V1-12V

Must

Unassigned

Engineering target - proposed

Not Run

REQUIREMENT
34
ELE-007
Draft
Electrical
SYS-008
ELE-007
ELE-007 - Electrical

Diagnostic connector pinout shall be keyed and defined.

ICD and physical inspection show no ambiguous voltage/polarity connections.

Inspection

Subsystem

V1-12V

Must

Unassigned

Engineering target - proposed

Not Run

REQUIREMENT
35
ELE-008
Draft
Electrical
SYS-009
ELE-008
ELE-008 - Electrical

PCB creepage, clearance and trace geometry shall meet the approved design rules.

Automated DRC zero blockers; independent safety spacing review passed.

Inspection

Subsystem

V1-12V

Must

Unassigned

Engineering target - proposed

Not Run

REQUIREMENT
36
ELE-009
Draft
Electrical
SYS-005
ELE-009
ELE-009 - Electrical

The BMS shall support a documented balancing strategy.

Balancing activation, inhibition, current and thermal budget tested.

Test

Subsystem

V1-12V

Must

Unassigned

Engineering target - proposed

TR-011

Not Run

REQUIREMENT
37
ELE-010
Draft
Electrical
SYS-002
ELE-010
ELE-010 - Electrical

Battery positive and negative polarity shall be unambiguous at external terminals.

Drawing, labels and as-built inspection agree.

Inspection

Subsystem

V1-12V

Must

Unassigned

Engineering target - proposed

HZ-004

Not Run

REQUIREMENT
38
ELE-011
Draft
Electrical
SYS-005
ELE-011
ELE-011 - Electrical

BMS power consumption shall remain within an approved storage and standby budget.

Measured operating/sleep current versus frozen current budget.

Test

Subsystem

V1-12V

Must

Unassigned

Engineering target - proposed

Not Run

REQUIREMENT
39
FW-001
Draft
Firmware
SYS-005
FW-001
FW-001 - Firmware

The firmware shall implement explicit INIT, IDLE, CHARGE, DISCHARGE, FAULT and SLEEP states.

All allowed and forbidden transitions covered by automated state table tests.

Test

Software

V1-12V

Must

Unassigned

Engineering target - proposed

TR-008

Not Run

REQUIREMENT
40
FW-002
Draft
Firmware
SYS-005
FW-002
FW-002 - Firmware

The firmware shall not override autonomous hardware protection to enable unsafe current.

Fault injection demonstrates external commands cannot bypass hardware protection.

Test

Software

V1-12V

Must

Unassigned

Engineering target - proposed

TR-009

HZ-012

Not Run

REQUIREMENT
41
FW-003
Draft
Firmware
ELE-001
FW-003
FW-003 - Firmware

The firmware shall acquire and validate per-cell voltage samples.

Unit tests cover scaling, range checking, invalid data and stale samples.

Test

Software

V1-12V

Must

Unassigned

Engineering target - proposed

Not Run

REQUIREMENT
42
FW-004
Draft
Firmware
ELE-003
FW-004
FW-004 - Firmware

The firmware shall maintain a signed coulomb-counting current integral.

Synthetic charge/discharge traces reproduce expected integrated Ah within numerical tolerance.

Test

Software

V1-12V

Must

Unassigned

Engineering target - proposed

TR-010

Not Run

REQUIREMENT
43
FW-005
Draft
Firmware
SYS-008
FW-005
FW-005 - Firmware

The firmware shall expose versioned diagnostic telemetry.

Protocol tests validate schema, units, timestamps and version negotiation.

Test

Software

V1-12V

Must

Unassigned

Engineering target - proposed

Not Run

REQUIREMENT
44
FW-006
Draft
Firmware
ELE-009
FW-006
FW-006 - Firmware

The firmware shall inhibit balancing under disallowed thermal/electrical states.

State-based tests cover all balancing inhibit conditions.

Test

Software

V1-12V

Must

Unassigned

Engineering target - proposed

Not Run

REQUIREMENT
45
FW-007
Draft
Firmware
SYS-005
FW-007
FW-007 - Firmware

The firmware shall retain a fault cause across a reset when specified by fault policy.

Reset/power-cycle test demonstrates event persists until authorized clearing.

Test

Software

V1-12V

Must

Unassigned

Engineering target - proposed

Not Run

REQUIREMENT
46
FW-008
Draft
Firmware
SYS-005
FW-008
FW-008 - Firmware

The firmware shall detect stalled critical tasks through watchdog supervision.

Injected task stall leads to defined fail-safe outcome.

Test

Software

V1-12V

Must

Unassigned

Engineering target - proposed

HZ-012

Not Run

REQUIREMENT
47
FW-009
Draft
Firmware
SYS-008
FW-009
FW-009 - Firmware

The firmware shall reject malformed or unauthorized configuration commands.

Protocol negative and authorization tests reject invalid writes.

Test

Software

V1-12V

Must

Unassigned

Engineering target - proposed

Not Run

REQUIREMENT
48
FW-010
Draft
Firmware
STK-005
FW-010
FW-010 - Firmware

Every firmware release shall retain build provenance and checksum.

Rebuild from pinned inputs reproduces version metadata and artifact hash policy.

Inspection

Software

V1-12V

Must

Unassigned

Engineering target - proposed

Not Run

REQUIREMENT
49
FW-011
Draft
Firmware
SYS-005
FW-011
FW-011 - Firmware

The firmware shall detect stale or invalid temperature data.

Loss/stuck-sensor simulated; safe-state policy passes all defined cases.

Test

Software

V1-12V

Must

Unassigned

Engineering target - proposed

HZ-006

Not Run

REQUIREMENT
50
FW-012
Draft
Firmware
SYS-008
FW-012
FW-012 - Firmware

The firmware shall support a controlled calibration data procedure.

Calibration revision and CRC verified; corrupt configuration rejected.

Test

Software

V1-12V

Must

Unassigned

Engineering target - proposed

Not Run

REQUIREMENT
51
MEC-001
Draft
Mechanical
SYS-001
MEC-001
MEC-001 - Mechanical

The pack shall secure four cells in the declared CAD orientation.

Assembly fit-check agrees with released drawing and stack tolerances.

Inspection

Subsystem

V1-12V

Must

Unassigned

Engineering target - proposed

Not Run

REQUIREMENT
52
MEC-002
Draft
Mechanical
SYS-009
MEC-002
MEC-002 - Mechanical

Cell restraints shall comply with the manufacturer compression limits.

Worst-case tolerance and clamping force verified against supplier envelope.

Analysis

Subsystem

V1-12V

Must

Unassigned

Engineering target - proposed

Not Run

REQUIREMENT
53
MEC-003
Draft
Mechanical
SYS-007
MEC-003
MEC-003 - Mechanical

Electrical insulation shall prevent accidental busbar-enclosure contact in all specified tolerances.

CAD clearance check and physical inspection against frozen spacing standard.

Inspection

Subsystem

V1-12V

Must

Unassigned

Engineering target - proposed

HZ-003

Not Run

REQUIREMENT
54
MEC-004
Draft
Mechanical
SYS-009
MEC-004
MEC-004 - Mechanical

The enclosure shall withstand the approved static mounting loads.

FEA and representative physical fixture test meet displacement/stress criteria.

Test

Subsystem

V1-12V

Must

Unassigned

Engineering target - proposed

HZ-010

Not Run

REQUIREMENT
55
MEC-005
Draft
Mechanical
SYS-009
MEC-005
MEC-005 - Mechanical

The mounting design shall avoid unacceptable resonances in the operational vibration profile.

Modal test correlated to model; resonant response compared to approved limits.

Test

Subsystem

V1-12V

Must

Unassigned

Engineering target - proposed

TR-013

HZ-009, HZ-010

Not Run

REQUIREMENT
56
MEC-006
Draft
Mechanical
SYS-007
MEC-006
MEC-006 - Mechanical

Busbar fastening shall use controlled fastener and torque specifications.

Assembly inspection documents torque procedure, washer and locking approach.

Inspection

Subsystem

V1-12V

Must

Unassigned

Engineering target - proposed

TR-014

HZ-009

Not Run

REQUIREMENT
57
MEC-007
Draft
Mechanical
STK-008
MEC-007
MEC-007 - Mechanical

Serviceable components shall be accessible without disturbing cell terminals unintentionally.

Service procedure dry-run demonstrates defined replacement and isolation sequence.

Demo

System

V1-12V

Must

Unassigned

Engineering target - proposed

Not Run

REQUIREMENT
58
MEC-008
Draft
Mechanical
SYS-009
MEC-008
MEC-008 - Mechanical

Mechanical BOM mass shall match CAD estimate within the approved discrepancy limit.

As-built pack mass reconciled to CAD/material mass budget.

Test

System

V1-12V

Must

Unassigned

Engineering target - proposed

Not Run

REQUIREMENT
59
MEC-009
Draft
Mechanical
SYS-009
MEC-009
MEC-009 - Mechanical

Critical dimensions and tolerances shall be present in manufacturing drawings.

Drawing review verifies dimensions, datum strategy, tolerances and revision labels.

Inspection

Subsystem

V1-12V

Must

Unassigned

Engineering target - proposed

Not Run

REQUIREMENT
60
THM-001
Draft
Thermal
SYS-003
THM-001
THM-001 - Thermal

The thermal model shall represent resistive losses in cells and power path.

Energy balance and I²R term unit tests pass.

Analysis

Model

V1-12V

Must

Unassigned

Engineering target - proposed

Not Run

REQUIREMENT
61
THM-002
Draft
Thermal
SYS-003
THM-002
THM-002 - Thermal

The thermal model shall represent ambient convection and thermal contact paths.

Parameters and boundary conditions documented with units and sources.

Inspection

Model

V1-12V

Must

Unassigned

Engineering target - proposed

Not Run

REQUIREMENT
62
THM-003
Draft
Thermal
SYS-003
THM-003
THM-003 - Thermal

Thermal response shall be estimated for nominal load and agreed duty cycle.

Transient prediction and assumptions exported for each approved scenario.

Analysis

Model

V1-12V

Must

Unassigned

Engineering target - proposed

Not Run

REQUIREMENT
63
THM-004
Draft
Thermal
SYS-003
THM-004
THM-004 - Thermal

The hottest measured cell location shall be included in a validation plan.

Thermocouple map identifies expected hotspot and representative measurements.

Inspection

System

V1-12V

Must

Unassigned

Engineering target - proposed

Not Run

REQUIREMENT
64
THM-005
Draft
Thermal
SYS-003
THM-005
THM-005 - Thermal

Thermal simulation accuracy shall be assessed against measured pack temperatures.

Correlation error and uncertainty reported across >= 3 agreed load profiles.

Test

System

V1-12V

Must

Unassigned

Engineering target - proposed

TR-012

HZ-011

Not Run

REQUIREMENT
65
THM-006
Draft
Thermal
SYS-005
THM-006
THM-006 - Thermal

The BMS shall block charging outside the permitted cell thermal range.

Boundary fault test shows expected cutoff and recovery behavior.

Test

System

V1-12V

Must

Unassigned

Engineering target - proposed

HZ-006

Not Run

REQUIREMENT
66
THM-007
Draft
Thermal
SYS-005
THM-007
THM-007 - Thermal

The BMS shall block discharge outside the permitted cell thermal range.

Boundary fault test shows expected cutoff and recovery behavior.

Test

System

V1-12V

Must

Unassigned

Engineering target - proposed

Not Run

REQUIREMENT
67
THM-008
Draft
Thermal
ELE-009
THM-008
THM-008 - Thermal

Cell balancing heat shall be represented in BMS thermal budget.

Worst-case balancing condition analysed and design review approved.

Analysis

Subsystem

V1-12V

Must

Unassigned

Engineering target - proposed

Not Run

REQUIREMENT
68
CAD-001
Draft
CAD
STK-005
CAD-001
CAD-001 - CAD

The master model shall generate the declared pack geometry from controlled parameters.

Regenerate 4S nominal variant without manual topology repair.

Demo

Model

V1-12V

Must

Unassigned

Engineering target - proposed

TR-015

Not Run

REQUIREMENT
69
CAD-002
Draft
CAD
STK-007
CAD-002
CAD-002 - CAD

The CAD generator shall support independent series count and cell dimensions within permitted families.

Parameterized 4S/8S/16S geometries generated; invalid combinations rejected.

Test

Model

V1-12V

Must

Unassigned

Engineering target - proposed

TR-016

Not Run

REQUIREMENT
70
CAD-003
Draft
CAD
SYS-001
CAD-003
CAD-003 - CAD

Each CAD cell shall reference an approved part geometry and tolerance set.

Part ID and dimensions match supplier drawing and imported material record.

Inspection

Model

V1-12V

Must

Unassigned

Engineering target - proposed

Not Run

REQUIREMENT
71
CAD-004
Draft
CAD
ELE-010
CAD-004
CAD-004 - CAD

The CAD assembly shall include terminals, busbars, BMS board, restraints and enclosure.

Released exploded assembly lists every defined subassembly.

Inspection

Model

V1-12V

Must

Unassigned

Engineering target - proposed

Not Run

REQUIREMENT
72
CAD-005
Draft
CAD
STK-006
CAD-005
CAD-005 - CAD

CAD part quantities shall be reconciled with the engineering BOM.

All released CAD component IDs map to counted BOM positions.

Test

Model

V1-12V

Must

Unassigned

Engineering target - proposed

TR-017

Not Run

REQUIREMENT
73
CAD-006
Draft
CAD
STK-004
CAD-006
CAD-006 - CAD

The build pipeline shall publish a browser-inspectable 3D derivative.

GLB/glTF derivative opens in target browsers with part IDs and units intact.

Test

Platform

V1-12V

Must

Unassigned

Engineering target - proposed

Not Run

REQUIREMENT
74
CAD-007
Draft
CAD
STK-005
CAD-007
CAD-007 - CAD

CAD outputs shall identify generator version and input parameter revision.

Manifest links source file, hash, parameter set and derived file hash.

Inspection

Platform

V1-12V

Must

Unassigned

Engineering target - proposed

Not Run

REQUIREMENT
75
CAD-008
Draft
CAD
MEC-003
CAD-008
CAD-008 - CAD

CAD automation shall detect electrical/physical clearance rule violations.

Synthetic interference test produces blocked release and exception record.

Test

Model

V1-12V

Must

Unassigned

Engineering target - proposed

Not Run

REQUIREMENT
76
SIM-001
Draft
Simulation
STK-005
SIM-001
SIM-001 - Simulation

The digital twin shall expose a 4-cell electrical equivalent-circuit model.

Model responds deterministically to frozen input scenario with baseline output.

Test

Model

V1-12V

Must

Unassigned

Engineering target - proposed

Not Run

REQUIREMENT
77
SIM-002
Draft
Simulation
STK-005
SIM-002
SIM-002 - Simulation

Each model run shall record parameter set, solver version and boundary conditions.

100% sampled runs reproduce metadata manifest and result hashes.

Inspection

Model

V1-12V

Must

Unassigned

Engineering target - proposed

HZ-011

Not Run

REQUIREMENT
78
SIM-003
Draft
Simulation
STK-005
SIM-003
SIM-003 - Simulation

The simulator shall distinguish model predictions from measured test data.

UI and exported report mark data origin at sample and series level.

Test

Platform

V1-12V

Must

Unassigned

Engineering target - proposed

Not Run

REQUIREMENT
79
SIM-004
Draft
Simulation
STK-005
SIM-004
SIM-004 - Simulation

The pack model shall report voltage, current, SOC, power and accumulated energy.

Numerical conservation/reference checks and display unit tests pass.

Test

Model

V1-12V

Must

Unassigned

Engineering target - proposed

TR-018

Not Run

REQUIREMENT
80
SIM-005
Draft
Simulation
STK-005
SIM-005
SIM-005 - Simulation

The pack model shall evaluate per-cell imbalance.

Unbalanced cell synthetic case generates distinct cell states and alerts.

Test

Model

V1-12V

Must

Unassigned

Engineering target - proposed

Not Run

REQUIREMENT
81
SIM-006
Draft
Simulation
THM-005
SIM-006
SIM-006 - Simulation

The simulation pipeline shall support parameter calibration without overwriting original measurement data.

Calibrated model version and input dataset hashes recorded separately.

Inspection

Model

V1-12V

Must

Unassigned

Engineering target - proposed

Not Run

REQUIREMENT
82
SIM-007
Draft
Simulation
MEC-005
SIM-007
SIM-007 - Simulation

The structural model shall support eigenfrequency/modal analysis.

Solver exports frequencies and modes with mesh, materials, constraints manifest.

Demo

Model

V1-12V

Must

Unassigned

Engineering target - proposed

Not Run

REQUIREMENT
83
SIM-008
Draft
Simulation
MEC-004
SIM-008
SIM-008 - Simulation

The structural solver shall support mesh convergence assessment.

At least three controlled mesh densities compared for critical response.

Analysis

Model

V1-12V

Must

Unassigned

Engineering target - proposed

Not Run

REQUIREMENT
84
SIM-009
Draft
Simulation
STK-004
SIM-009
SIM-009 - Simulation

Interactive simulation shall return a useful lightweight response within the target UI budget.

95th percentile local scenario calculation <2 seconds on target test workstation.

Test

Platform

V1-12V

Must

Unassigned

Engineering target - proposed

Not Run

REQUIREMENT
85
SIM-010
Draft
Simulation
STK-005
SIM-010
SIM-010 - Simulation

Invalid model parameters shall be rejected before execution.

Schema/physics guards reject negative resistance, zero mass, bad series count.

Test

Platform

V1-12V

Must

Unassigned

Engineering target - proposed

TR-019

Not Run

REQUIREMENT
86
PLT-001
Draft
Platform
STK-004
PLT-001
PLT-001 - Platform

Authorized users shall access released projects through modern browsers.

Desktop and mobile browser acceptance matrix passes.

Test

Platform

V1-12V

Must

Unassigned

Engineering target - proposed

Not Run

REQUIREMENT
87
PLT-002
Draft
Platform
STK-004
PLT-002
PLT-002 - Platform

Project access shall require authenticated identity and role authorization.

Negative tests deny unauthenticated and cross-project access.

Test

Platform

V1-12V

Must

Unassigned

Engineering target - proposed

TR-020

Not Run

REQUIREMENT
88
PLT-003
Draft
Platform
STK-004
PLT-003
PLT-003 - Platform

Large CAD and simulation artifacts shall be stored in Google Cloud Storage.

Artifact upload/download integrity hash matches and metadata indexed.

Test

Platform

V1-12V

Must

Unassigned

Engineering target - proposed

Not Run

REQUIREMENT
89
PLT-004
Draft
Platform
STK-005
PLT-004
PLT-004 - Platform

Requirement documents shall be managed as Git-versioned text sources.

A change is traceable to commit, author, diff and review decision.

Inspection

Platform

V1-12V

Must

Unassigned

Engineering target - proposed

Not Run

REQUIREMENT
90
PLT-005
Draft
Platform
STK-004
PLT-005
PLT-005 - Platform

The UI shall display read-only released CAD model derivatives.

Released revision loads and independent user cannot mutate master CAD.

Test

Platform

V1-12V

Must

Unassigned

Engineering target - proposed

Not Run

REQUIREMENT
91
PLT-006
Draft
Platform
STK-005
PLT-006
PLT-006 - Platform

Each simulation result shall reference immutable input and executable versions.

Run manifest contains source commit, params checksum, solver version.

Inspection

Platform

V1-12V

Must

Unassigned

Engineering target - proposed

Not Run

REQUIREMENT
92
PLT-007
Draft
Platform
STK-004
PLT-007
PLT-007 - Platform

Long simulation jobs shall execute outside synchronous web requests.

Job survives browser disconnect; status and result remain retrievable.

Test

Platform

V1-12V

Must

Unassigned

Engineering target - proposed

TR-021

Not Run

REQUIREMENT
93
PLT-008
Draft
Platform
STK-004
PLT-008
PLT-008 - Platform

Cloud storage objects shall be recoverable under the approved backup policy.

Documented restore drill recovers deliberately removed test dataset.

Test

Platform

V1-12V

Must

Unassigned

Engineering target - proposed

TR-022

HZ-015

Not Run

REQUIREMENT
94
PLT-009
Draft
Platform
STK-004
PLT-009
PLT-009 - Platform

Remote application secrets shall not be embedded in downloaded browser assets.

Security review and secret scanning identify no exposed credentials.

Inspection

Platform

V1-12V

Must

Unassigned

Engineering target - proposed

Not Run

REQUIREMENT
95
PLT-010
Draft
Platform
STK-005
PLT-010
PLT-010 - Platform

The system shall maintain immutable release manifests.

Release includes refs/hashes for requirements, PCB, CAD, FW, BOM, test evidence.

Test

Platform

V1-12V

Must

Unassigned

Engineering target - proposed

TR-024

HZ-015

Not Run

REQUIREMENT
96
PLT-011
Draft
Platform
STK-005
PLT-011
PLT-011 - Platform

The UI shall link each failed test to its governing requirement.

Select failed test and navigate to matching requirement ID and commit.

Demo

Platform

V1-12V

Must

Unassigned

Engineering target - proposed

Not Run

REQUIREMENT
97
PLT-012
Draft
Platform
STK-004
PLT-012
PLT-012 - Platform

The platform shall refuse hazardous remote physical-bench actuation without local enable.

Authorization negative test and physical local interlock demonstration pass.

Test

Platform

V1-12V

Must

Unassigned

Engineering target - proposed

TR-023

HZ-013

Not Run

REQUIREMENT
98
PLT-013
Draft
Platform
STK-005
PLT-013
PLT-013 - Platform

The platform shall preserve source measurements separately from derived simulation results.

Original datasets content-addressed; transformations separately versioned.

Inspection

Platform

V1-12V

Must

Unassigned

Engineering target - proposed

Not Run

REQUIREMENT
99
PLT-014
Draft
Platform
STK-004
PLT-014
PLT-014 - Platform

Users shall see run state, errors, and diagnostic references for failed jobs.

Forced solver failure yields log link, failure code, and no false 'passed' state.

Test

Platform

V1-12V

Must

Unassigned

Engineering target - proposed

Not Run

REQUIREMENT
100
VER-001
Draft
Verification
STK-005
VER-001
VER-001 - Verification

Every approved engineering requirement shall have a verification method and acceptance criterion.

No approved requirements have blank method, criterion, or verification ID.

Inspection

Process

V1-12V

Must

Unassigned

Engineering target - proposed

Not Run

REQUIREMENT
101
VER-002
Draft
Verification
STK-005
VER-002
VER-002 - Verification

Safety-critical requirements shall have a hazard link and review approval.

100% safety-tagged requirements linked to at least one risk or safety rationale.

Inspection

Process

V1-12V

Must

Unassigned

Engineering target - proposed

Not Run

REQUIREMENT
102
VER-003
Draft
Verification
STK-005
VER-003
VER-003 - Verification

Test cases shall identify setup, stimuli, expected result, actual result and artifacts.

Sample tests contain all fields and independent rerun possible.

Inspection

Process

V1-12V

Must

Unassigned

Engineering target - proposed

Not Run

REQUIREMENT
103
VER-004
Draft
Verification
STK-005
VER-004
VER-004 - Verification

Verification results shall distinguish Passed, Failed, Blocked and Not Run.

Report schema validation rejects ambiguous status labels.

Test

Process

V1-12V

Must

Unassigned

Engineering target - proposed

Not Run

REQUIREMENT
104
VER-005
Draft
Verification
STK-005
VER-005
VER-005 - Verification

The system shall prohibit release on unresolved critical verification failures.

Synthetic critical failure blocks release gate automatically.

Test

Process

V1-12V

Must

Unassigned

Engineering target - proposed

TR-025

Not Run

REQUIREMENT
105
VER-006
Draft
Verification
STK-005
VER-006
VER-006 - Verification

Test equipment shall be linked to calibration status and uncertainty.

Each measurement-based test has instrument ID, calibration date, uncertainty.

Inspection

Process

V1-12V

Must

Unassigned

Engineering target - proposed

Not Run

REQUIREMENT
106
VER-007
Draft
Verification
STK-005
VER-007
VER-007 - Verification

Requirement changes after baseline shall trigger impact analysis.

Diff lists affected architecture elements, CAD, PCB, FW and test IDs.

Demo

Process

V1-12V

Must

Unassigned

Engineering target - proposed

Not Run

REQUIREMENT
107
VER-008
Draft
Verification
STK-005
VER-008
VER-008 - Verification

System validation shall be distinguished from specification verification.

V&V plan provides separate user-need acceptance and compliance evidence.

Review

Process

V1-12V

Must

Unassigned

Engineering target - proposed

Not Run

REQUIREMENT
108
VER-009
Draft
Verification
STK-005
VER-009
VER-009 - Verification

Fault injection shall never energize an unguarded hazardous battery bench remotely.

Interlock validation rejects remote command in unsafe configuration.

Test

Process

V1-12V

Must

Unassigned

Engineering target - proposed

HZ-013

Not Run

REQUIREMENT
109
VER-010
Draft
Verification
STK-005
VER-010
VER-010 - Verification

Regression suites shall run on every controlled software change.

CI report records pass/fail, commit and test count for each merge.

Test

Process

V1-12V

Must

Unassigned

Engineering target - proposed

Not Run

REQUIREMENT
110
BOM-001
Draft
BOM
STK-006
BOM-001
BOM-001 - BOM

Every approved purchasable part shall have a unique ID and revision.

100% released parts have part numbers, approved footprint or spec and revision.

Inspection

Process

V1-12V

Must

Unassigned

Engineering target - proposed

Not Run

REQUIREMENT
111
BOM-002
Draft
BOM
STK-006
BOM-002
BOM-002 - BOM

The BOM shall separate cell, BMS, enclosure, harness and assembly cost.

Cost rollup correctly sums subassembly and unit totals.

Test

Process

V1-12V

Must

Unassigned

Engineering target - proposed

Not Run

REQUIREMENT
112
BOM-003
Draft
BOM
STK-006
BOM-003
BOM-003 - BOM

Unit cost shall be calculated at prototype, 100 and 10000-unit quantities.

Cost rollup produces price breaks with quote dates and currency.

Test

Process

V1-12V

Must

Unassigned

Engineering target - proposed

TR-026

Not Run

REQUIREMENT
113
BOM-004
Draft
BOM
STK-006
BOM-004
BOM-004 - BOM

Approved alternates shall preserve form-fit-function and qualification evidence.

Replacement cannot be marked approved without referenced validation.

Inspection

Process

V1-12V

Must

Unassigned

Engineering target - proposed

Not Run

REQUIREMENT
114
BOM-005
Draft
BOM
STK-006
BOM-005
BOM-005 - BOM

The platform shall flag obsolete or single-source critical parts.

Artificial supplier change triggers lifecycle risk flag.

Test

Platform

V1-12V

Must

Unassigned

Engineering target - proposed

Not Run

REQUIREMENT
115
BOM-006
Draft
BOM
STK-006
BOM-006
BOM-006 - BOM

The system shall calculate estimated landed cost using separated assumptions.

Formula validation covers price, scrap, assembly, freight and test yield.

Test

Platform

V1-12V

Must

Unassigned

Engineering target - proposed

Not Run

REQUIREMENT
116
BOM-007
Draft
BOM
STK-006
BOM-007
BOM-007 - BOM

Any BOM cost comparison shall identify assumptions and quote validity.

100% review samples show quote date and currency normalization.

Inspection

Process

V1-12V

Must

Unassigned

Engineering target - proposed

Not Run

REQUIREMENT
117
MFG-001
Draft
Manufacturing
STK-006
MFG-001
MFG-001 - Manufacturing

The pack shall have a defined assembly process with controlled order of operations.

Approved work instructions identify each critical step and hazard.

Inspection

Process

V1-12V

Must

Unassigned

Engineering target - proposed

Not Run

REQUIREMENT
118
MFG-002
Draft
Manufacturing
SYS-007
MFG-002
MFG-002 - Manufacturing

Pack terminal, fuse and busbar assembly shall have prescribed inspection checks.

EOL checklist verifies polarity, continuity and fastener records.

Test

System

V1-12V

Must

Unassigned

Engineering target - proposed

HZ-004

Not Run

REQUIREMENT
119
MFG-003
Draft
Manufacturing
STK-005
MFG-003
MFG-003 - Manufacturing

Each assembled pack shall carry serial and test result identity.

Physical label resolves to build record, lot, FW and test data.

Test

System

V1-12V

Must

Unassigned

Engineering target - proposed

TR-027

Not Run

REQUIREMENT
120
MFG-004
Draft
Manufacturing
STK-006
MFG-004
MFG-004 - Manufacturing

The project shall calculate yield-adjusted production BOM cost.

Production estimate formula tests pass for multiple scrap/yield inputs.

Test

Process

V1-12V

Must

Unassigned

Engineering target - proposed

Not Run

REQUIREMENT
121
MFG-005
Draft
Manufacturing
STK-003
MFG-005
MFG-005 - Manufacturing

Release documents shall include safe shipping and handling requirements.

Reviewed handling procedure and applicable transport compliance matrix exist.

Inspection

Process

V1-12V

Must

Unassigned

Engineering target - proposed

Not Run

REQUIREMENT
122
MFG-006
Draft
Manufacturing
STK-005
MFG-006
MFG-006 - Manufacturing

Firmware programming and configuration shall be logged during end-of-line test.

EOL record captures image hash, settings CRC and measured calibration data.

Test

System

V1-12V

Must

Unassigned

Engineering target - proposed

Not Run

REQUIREMENT
123
SCL-001
Draft
Scale-up
STK-007
SCL-001
SCL-001 - Scale-up

The family architecture shall separate hardware-dependent protection from portable firmware logic.

Design review identifies abstraction interfaces and variant-specific drivers.

Inspection

Architecture

V2+

Must

Unassigned

Engineering target - proposed

Not Run

REQUIREMENT
124
SCL-002
Draft
Scale-up
STK-007
SCL-002
SCL-002 - Scale-up

The platform shall reject designs where maximum pack voltage exceeds rated components.

Static rule uses cell upper limit * series count against rated design envelope.

Test

Platform

V2+

Must

Unassigned

Engineering target - proposed

HZ-014

Not Run

REQUIREMENT
125
SCL-003
Draft
Scale-up
STK-007
SCL-003
SCL-003 - Scale-up

The 8S variant shall receive its own sensing and power protection review.

8S architecture sign-off includes sensor, FET, charger, thermal and fuse design.

Review

Architecture

V2+

Must

Unassigned

Engineering target - proposed

Not Run

REQUIREMENT
126
SCL-004
Draft
Scale-up
STK-007
SCL-004
SCL-004 - Scale-up

The 16S variant shall receive separate voltage/clearance and protection validation.

16S revision has independent electrical and mechanical verification plan.

Review

Architecture

V3+

Must

Unassigned

Engineering target - proposed

Not Run

REQUIREMENT
127
SCL-005
Draft
Scale-up
STK-007
SCL-005
SCL-005 - Scale-up

The 72 V-class variant shall define nominal and absolute maximum voltage explicitly.

System datasheet declares chemistry, series count and maximum charged voltage.

Inspection

Architecture

V4+

Must

Unassigned

Engineering target - proposed

HZ-014

Not Run

REQUIREMENT
128
SCL-006
Draft
Scale-up
STK-007
SCL-006
SCL-006 - Scale-up

Higher-voltage variants shall be assessed for isolation and precharge requirements.

Hazard/architecture review documents whether isolation and precharge are needed.

Analysis

Architecture

V4+

Must

Unassigned

Engineering target - proposed

Not Run

REQUIREMENT
129
SCL-007
Draft
Scale-up
STK-007
SCL-007
SCL-007 - Scale-up

Variants shall reuse requirement/test templates only after applicability review.

Each inherited requirement lists applicable variants and any revised criterion.

Inspection

Process

V2+

Must

Unassigned

Engineering target - proposed

Not Run

REQUIREMENT
130
SCL-008
Draft
Scale-up
STK-007
SCL-008
SCL-008 - Scale-up

Series-connected modules shall be validated as one coordinated pack protection system.

System fault model reviews worst-case module trip, imbalance, and unintended reclose.

Analysis

System

V4+

Must

Unassigned

Engineering target - proposed

Not Run